Facility scorecard, format example

Blackwater Ridge Campus

Operator: Northfork Digital (fictional). Host region: Marrow Run Township and Carbon Fork County, Pennsylvania (fictional). 160 MW IT load energized of 240 MW at full build-out.
Assessment period: January 1 to December 31, 2025. Site visit: February 10 to 12, 2026. Certification Committee decision: March 26, 2026. Next re-audit: first quarter 2027.
This scorecard is a worked example of the published format. No facility has been assessed under the standard, and the facility, operator, county, and every figure are fictional.

Tier

Provisional

78 of 100 points. Every pillar clears the 12-point Full-tier floor: Water and Resource Efficiency 13, Additive Energy 14, Siting and Local Environment 18, Fiscal Accountability 15, Verified Community Benefit 18. Full tier requires 80 points in total; this facility is two short.

Water and Resource Efficiency13 / 20
Additive Energy14 / 20
Siting and Local Environment18 / 20
Fiscal Accountability15 / 20
Verified Community Benefit18 / 20

Where the points were lost

Twenty-two points, and two of them decide the tier. The largest single loss is item F2: the facility has published no independent fiscal impact analysis, so neither the county nor its residents can see the value of the twenty-year abatement set against the public cost of the infrastructure the campus requires. That is five points and it would be the cheapest five points on this scorecard to earn. Heat recovery accounts for four more; the facility exports none, and holds only readiness credit for an inspected tie-in and a feasibility study. Energy accounts for six: hourly matching at 71% sits in the middle band, and only 31% of matched supply is additive. Two points are lost at item L3 because the permit caps generator hours without prohibiting non-emergency dispatch, and two at item C4 because committed contributions come to roughly 1.4% of disclosed capital investment, inside the lower band. Water usage effectiveness of 0.21 L/kWh costs three, which the operator attributes to a hybrid trim mode used on nine days in July 2025, disclosed.

The facility is two points below the Full tier threshold and clears the 12-point floor in every pillar. Publishing the fiscal analysis alone would carry it over.

Pillar One: Water and Resource Efficiency 13 / 20

ItemRequirementPointsEvidence and assessor note
W1Closed-loop, non-evaporative cooling, verified on site5 / 5Closed loop confirmed on site visit; makeup water metered at 1.1 m3/day
W2WUE per ISO/IEC 30134-9, trailing 12 months2 / 50.21 L/kWh; below the 0.10 band, within the 0.30 band
W3Zero potable water for cooling in normal operation2 / 2Emergency backup capped at 40,000 gal/yr; 0 used
W4Source and 90-day demand disclosure; authority consultation; no pretreatment discharge2 / 2Disclosed 2025-03; acknowledgment on file; discharge reconciled
R1Measured ERF per ISO/IEC 30134-60 / 3No heat export in the assessment period
R2Committed heat reuse pathway1 / 2Feasibility study naming the county technical centre greenhouse and a district loop; no signed offtake
R3Export-ready design: heat exchanger and tie-in installed1 / 1Tie-in inspected; pipe stubbed to the property line

Pillar Two: Additive Energy 14 / 20

ItemRequirementPointsEvidence and assessor note
E1Hourly matched carbon-free energy, trailing 12 months, same grid region7 / 1071% hourly matched; within the 70% band
E2Share of matched supply from additive generation2 / 531% from a solar project reaching commercial operation 14 months before the facility
E3Interconnection terms, load ramp, 90-day disclosure, ratepayer analysis, full upgrade cost4 / 4All four conditions met; ramp published to 2028
E4Demand response from load or storage, not on-site combustion1 / 1Six events served from load shifting, 2025

Pillar Three: Siting and Local Environment 18 / 20

ItemRequirementPointsEvidence and assessor note
S1Not sited in a highest-quintile burden tract for air, groundwater, or hazardous waste4 / 4State screening tool, assessed 2024-09: tract in the third quintile for air quality, second for groundwater
S2No siting on a contaminated or priority-list site; land conversion disclosed2 / 2Phase I and II clean; 118 acres former row crop, disclosed with agricultural classification
L1Night sound at the nearest residential property line, against ambient and an absolute ceiling6 / 6Ambient 41 dBA; measured 44 to 47 dBA across the year, inside the stricter of the two tests after the May chiller fan replacement
L2Ambient survey published; quarterly monitoring by a party not contracted by the operator2 / 2Survey published 2024-11; township contractor; four quarters published, longest lag 12 days
L3Tier 4 engines; run hours capped and published; no demand-response or economic dispatch2 / 4All engines Tier 4; 38 hours published for 2025. The permit caps annual hours but does not prohibit non-emergency dispatch; the operator has committed to seek that condition at renewal
L4Dark-sky lighting; no measurable trespass; photometric plan published1 / 1Night inspection found no measurable trespass
L5Buffers at or above the greater of local requirement or 100 feet; plant screened1 / 1140-foot buffer at the Quarry Road boundary; generators and chillers enclosed

Pillar Four: Fiscal Accountability 15 / 20

ItemRequirementPointsEvidence and assessor note
F1All abatements, exemptions, PILOT and incentive agreements published; no NDA over any term5 / 5County abatement and township agreement published 2024-12; no NDA
F2Independent fiscal impact analysis published before first approval, over the full abatement term0 / 5No fiscal impact analysis has been published. The county's own estimate of forgone revenue over the 20-year abatement is not public. This is the facility's single largest scoring loss
F3Community fund contributions secured by letter of credit, escrow, or parent guarantee, two years minimum5 / 5Letter of credit for $560,000, approximately two years of committed payments, issued by a federally insured bank
F4First responder training at no cost; incident cost recovery above a stated threshold3 / 318 members trained on electrical and battery systems; recovery above $25,000 per incident agreed with the fire company
F5Construction and operational traffic study published; road improvements funded2 / 2Study published 2024-08; Quarry Road improvements funded and complete

Pillar Five: Verified Community Benefit 18 / 20

ItemRequirementPointsEvidence and assessor note
C1Resident-majority council, Council-contracted facilitator, stipends and paid coordinator3 / 3Five of seven seats held by residents; stipends paid from the fund
C2Participatory needs assessment2 / 2Published 2025-03; 14 sessions, 212 participants
C3Matched contribution under a signed fund agreement, with equipment refresh as a triggering event4 / 4Operator share and buyer match received on schedule, six quarters; refresh clause executed 2026-02
C4Committed contributions as a share of total capital investment2 / 4Committed contributions over the 20-year term are approximately 1.4% of disclosed capital investment of $1.9 billion; within the 1.0% band, below the 2.0% band
C5Quarterly public reporting against every commitment; agreement published3 / 3Six of six reports within 30 days; agreement public
C6Local hiring and contracting results, plus a credentialed training pathway2 / 244% of operating roles held by county residents; 22 apprentices enrolled at the county technical centre
C7Digital access assessed and fundable1 / 1Broadband gap identified; middle-mile fibre funded; route assessed
C8Electronic waste: lifecycle plan with the reuse and recycling chain published1 / 1Plan published 2025-06; destination facilities named for the 2028 refresh

Program designer and disclosure

The facility's community benefit program was designed by Baseload Commons, a recognized program designer owned by the Council's convener. In accordance with the Governance and Independence Policy, the convener took no part in assessor assignment, the assessment, or the Certification Committee's decision, and had no access to the draft report before the decision. Assessors confirmed no prior involvement with the facility or the designer's work. The program is facilitated by a facilitator contracted by the Council, not by the operator or the designer.

Community fund

QuarterOperator contributionBuyer matchGrants paidBalanceFoundation statement
Q1 2025$120,000$0$0$111,600Statement
Q2 2025$120,000$60,000$120,000$159,000Statement
Q3 2025$160,000$80,000$450,000($67,800)*Statement
Q4 2025$160,000$95,000$300,000($75,650)*Statement

* Negative balances reflect grants committed ahead of receipts under a bridge arrangement with the foundation, disclosed in the fund statement and repaid from Q1 2026 inflows. The assessor notes this as a governance point to watch, not a finding. Cumulative to June 30, 2026: $1,333,000 received, $965,000 granted, $93,310 retained for facilitation, assessment and custody.

Community validation

Nine members of the advisory council were interviewed without the operator present. All confirmed that priorities were set by the council from the needs assessment, that the operator holds no vote on grants, and that minutes are posted. Two raised the late posting of the March 2026 minutes; one raised construction traffic on Quarry Road, referred to the township's complaint process. The fiscal agent confirmed receipt and disbursement of every payment listed above. Complaints received through the Council's public channel during the assessment period: one, concerning nighttime noise in May 2025, investigated and closed after the operator replaced a chiller fan; readings returned to 44 to 47 dBA.

Conditions and status

  • Decommissioning and continuity: the operator's decommissioning and site restoration plan is due December 2026 under the community benefit agreement and under Section 9 of the standard. If it is not filed by the next re-audit, the facility is capped at Entry tier.
  • Material misstatement: none found. All submitted claims reconciled to utility, water authority, interconnection, and foundation records.
  • Status: Certified, Provisional tier. Not suspended.

Record

This scorecard, every quarterly fund statement, and the assessment summary remain published after any re-tiering, suspension, sale, or decommissioning, and are never removed at the operator's request. Assessment conducted by a Lead Technical Assessor (licensed PE), an Energy Analyst, and the Council's Community Assessor, with second review; roles are published, names are available on request to the Certification Committee.