Facility scorecard, format example

Blackwater Ridge Campus

Operator: Northfork Digital (fictional). Host region: Marrow Run Township and Carbon Fork County, Pennsylvania (fictional). 160 MW IT load energized of 240 MW at full build-out.
Assessment period: January 1 to December 31, 2025. Site visit: February 10 to 12, 2026. Certification Committee decision: March 26, 2026. Next re-audit: first quarter 2027.
This scorecard is a worked example of the published format. No facility has been assessed under the standard, and the facility, operator, county, and every figure are fictional.

Tier

Provisional

73 of 100 points. Floors met: Water 22, Energy 19, Community 25, all at or above 10; Heat Recovery 7, at or above 5. Full tier requires 80 points, 15 in every pillar, and measured heat reuse.

Water Stewardship22 / 25
Additive Energy19 / 25
Heat Recovery7 / 25
Verified Community Benefit25 / 25

Where the points were lost

Heat recovery. The facility exports no heat in the assessment period and scores 7 of 25 on readiness alone: an inspected tie-in and a feasibility study naming two offtakers. A signed offtake agreement would add 3 points; measured reuse at ERF 0.05 would add 8 and, with the other pillars unchanged, would bring the facility to the Full tier threshold. Water usage effectiveness of 0.21 L/kWh sits in the middle band; the operator attributes the gap to a hybrid trim mode used on 9 days in July 2025, disclosed. Hourly matched energy at 71% sits in the 70% band; the 85% band would require an additional 30 MW of same-region carbon-free supply.

Pillar One: Water Stewardship 22 / 25

ItemRequirementPointsEvidence and assessor note
W1Closed-loop, non-evaporative cooling in normal operation, verified on site10 / 10Closed loop confirmed on site visit; makeup water metered at 1.1 m3/day
W2WUE per ISO/IEC 30134-9, trailing 12 months3 / 60.21 L/kWh; below the 0.10 band, within the 0.30 band
W3Zero potable water for cooling in normal operation4 / 4Emergency backup capped at 40,000 gal/yr in the assessment plan; 0 used
W4Withdrawal source and 90-day demand disclosure; water authority consultation3 / 3Disclosed 2025-03; authority acknowledgment on file
W5No industrial pretreatment discharge; records reconciled2 / 2Reconciled to authority records

Pillar Two: Additive Energy 19 / 25

ItemRequirementPointsEvidence and assessor note
E1Hourly matched carbon-free energy, trailing 12 months, same grid region9 / 1271% hourly matched; within the 70% band
E2Share of matched supply from additive generation3 / 631% from a solar project reaching commercial operation 14 months before the facility; within the 25% band
E3Interconnection terms, load ramp, 90-day disclosure, ratepayer analysis, full upgrade cost5 / 5All four conditions met; ramp published to 2028
E4Curtailment or demand response participation2 / 2Enrolled in utility demand response; 6 events, 2025

Pillar Three: Heat Recovery 7 / 25

ItemRequirementPointsEvidence and assessor note
H1Measured ERF per ISO/IEC 30134-6, trailing 12 months0 / 15No export in the assessment period
H2Committed reuse pathway2 / 5Feasibility study complete naming the county technical center greenhouse and a district loop; no signed offtake
H3Export-ready design: heat exchanger and tie-in installed5 / 5Tie-in inspected; pipe stubbed to the property line

Pillar Four: Verified Community Benefit 25 / 25

ItemRequirementPointsEvidence and assessor note
C1Resident-majority advisory council with Council-contracted facilitator5 / 5Five of seven seats held by residents; facilitator contracted 2025-01
C2Participatory needs assessment4 / 4Published 2025-03; 14 sessions, 212 participants
C3Enrolled in the matched contribution mechanism under a signed fund agreement7 / 7Operator share and buyer match received on schedule, six quarters
C4Quarterly public reporting against every commitment; agreement published3 / 3Six of six reports within 30 days; agreement public
C5No NDAs over incentive terms2 / 2Township agreement public since 2024-12
C6Local hiring commitments with published results2 / 244% of operating roles; target 40%
C7Digital access assessed and fundable2 / 2Broadband gap identified; middle-mile fiber funded; route assessed

Program designer and disclosure

The facility's community benefit program was designed by Baseload Commons, a recognized program designer owned by the Council's convener. In accordance with the Governance and Independence Policy, the convener took no part in assessor assignment, the assessment, or the Certification Committee's decision, and had no access to the draft report before the decision. Assessors confirmed no prior involvement with the facility or the designer's work. The program is facilitated by a facilitator contracted by the Council, not by the operator or the designer.

Community fund

QuarterOperator contributionBuyer matchGrants paidBalanceFoundation statement
Q1 2025$120,000$0$0$111,600Statement
Q2 2025$120,000$60,000$120,000$159,000Statement
Q3 2025$160,000$80,000$450,000($67,800)*Statement
Q4 2025$160,000$95,000$300,000($75,650)*Statement

* Negative balances reflect grants committed ahead of receipts under a bridge arrangement with the foundation, disclosed in the fund statement and repaid from Q1 2026 inflows. The assessor notes this as a governance point to watch, not a finding. Cumulative to June 30, 2026: $1,333,000 received, $965,000 granted, $93,310 retained for facilitation, assessment and custody.

Community validation

Nine members of the advisory council were interviewed without the operator present. All confirmed that priorities were set by the council from the needs assessment, that the operator holds no vote on grants, and that minutes are posted. Two raised the late posting of the March 2026 minutes; one raised construction traffic on Quarry Road, referred to the township's complaint process. The fiscal agent confirmed receipt and disbursement of every payment listed above. Complaints received through the Council's public channel during the assessment period: one, concerning nighttime noise in May 2025, investigated and closed after the operator replaced a chiller fan; readings returned to 44 to 47 dBA.

Conditions and status

  • Decommissioning and continuity: the operator's decommissioning and site restoration plan is due December 2026 under the community benefit agreement and under Section 9 of the standard. If it is not filed by the next re-audit, the facility is capped at Entry tier.
  • Material misstatement: none found. All submitted claims reconciled to utility, water authority, interconnection, and foundation records.
  • Status: Certified, Provisional tier. Not suspended.

Record

This scorecard, every quarterly fund statement, and the assessment summary remain published after any re-tiering, suspension, sale, or decommissioning, and are never removed at the operator's request. Assessment conducted by a Lead Technical Assessor (licensed PE), an Energy Analyst, and the Council's Community Assessor, with second review; roles are published, names are available on request to the Certification Committee.